Site work follows a logical order because each step depends on the one before it. Here is how a typical ProBuilt job runs.
1. First call and site walk
You tell us the address or parcel and what you want to build. We look at aerial and county parcel maps, then walk the property, ideally with you. We're looking at access, slope, soil, trees, water (creeks, springs, low spots), existing utilities and neighbors.
2. Scope and written quote
We put the job in writing: what we'll clear, where the pad sits and at what elevation, how the driveway runs, how water will be handled, and what's not included. Clear scope is the best protection against surprises for both of us.
3. Permits and paperwork
Depending on the county and the size of the job, this may include:
- A land disturbance permit from the county or city
- Georgia EPD construction stormwater coverage (a notice of intent) for one acre or more of disturbance
- A driveway permit from the county or GDOT
- Environmental Health septic approval for lots without sewer
- Georgia 811 utility locates before any digging
See our site work permits guide for details.
4. Erosion control goes in first
Silt fence, a stone construction exit and inlet protection go in before the first tree is cut. That's both the law and good practice. See erosion control.
5. Clearing and grubbing
We clear the approved area, protect the trees you're keeping, and remove stumps and roots where there will be a pad, a drive or fill. See land clearing.
6. Grading and pads
Topsoil is stripped and saved, the site is cut and filled toward final elevations, and fill is compacted in lifts. Pads are built and checked for height. See grading & excavation and building pads.
7. Utilities, drainage and driveway
Trenches for water, sewer, power and storm lines are dug, bedded and backfilled. The driveway gets its base stone. Drainage structures go in.
8. Final grade and stabilization
After construction, we return to set the final grade so water moves away from the building, spread topsoil and seed or straw. Temporary erosion controls come out once the ground is stabilized.