We don't publish price lists, because a price that ignores the lot isn't worth much. Here's what actually drives the cost of site work, roughly in order of impact.
1. How much dirt moves, and where it goes
The biggest swing in most grading jobs is whether the site balances. If the cut equals the fill, dirt just moves around the site. If the site needs fill brought in, or has extra spoil to haul off, trucking can rival everything else in the job.
2. Slope
Steeper lots need more cut and fill for the same flat pad, longer driveway routes, more erosion control and sometimes retaining walls.
3. Clearing density
An open pasture is quick. Dense pines, big hardwoods and heavy underbrush take longer to clear, grub and process, and debris disposal adds up. Saving some trees takes more care but costs less to stabilize.
4. Soil and rock
Good red clay is easy to work when it's dry. Wet, soft soil may need undercutting and replacement, or stone and fabric. Rock that needs a hammer or blasting changes everything, which is why we look for outcrops on the site walk.
5. Access and space
Can trucks and equipment get in without a temporary drive? Is there room to stockpile topsoil and turn around? Tight in-town lots in Athens take longer than open rural ground.
6. Water
Creeks and buffers, springs, wet areas and drainage onto or off the property all add design and work. Storm pipe, culverts and detention are often line items of their own.
7. Permits, plans and erosion control
One acre of disturbance brings in state stormwater requirements, with more controls, inspections and paperwork. Larger projects need engineered plans. See site work permits.
8. Weather and season
Clay can't be compacted properly when it's soaked. Wet seasons stretch schedules, and good contractors will wait instead of building on mud.
Getting an accurate quote
Send us the address or parcel, a survey or plat if you have one, and your plan or rough footprint. Then let us walk it. Our lot prep checklist helps you gather the rest.